Michels aces challenging earth retention project

Michels provided support, literally, to a project on an Illinois university campus that will ultimately transform a surface parking lot into an athletic field.

Michels was selected to design and build internal bracing for the rehabilitation of a subsurface 5-million-gallon freshwater holding tank. The crux of Michels’ work was the installation and bracing of an earth retention system (ERS) spanning 440 wall feet. The two-level ERS design consisted of:

  • 15,800-square-feet of sheeting
  • 10 corner struts and five cross struts on the upper level
  • six corner struts and four cross struts on the lower level

Following installation of the bracing system, concrete was poured around the freshwater tank base.

Michels was one of only a few contractors willing to take on the challenging project. The project site was located on a very tight site next to a 7-story residence hall that houses 422 students. Michels implemented extensive safety precautions, including fencing around the project site, construction barrels and traffic control personnel to assist with movement of the university’s 20,000 students. Due to university regulations, work hours also had to reflect the university's standards during school hours, finals and graduation.

After Michels’ work was finished, the university built an athletic field on the surface where a parking lot had been located. Michels portion of the work was completed before students returned to campus.

Click here to learn more about our earth retention system services. 

Share!
Enjoy the article so far? Recommend it to your friends and peers.

Michels Corporation 
Copyright © 2019

Individual commitment to a group effort - that is what makes a team work, a company work, a society work, a civilization work.

Vince Lombardi

Great teamwork can do great things.

Contact Us