Foundations

I-74 Mississippi River Bridge

I-74 Mississippi River Bridge

Scope

Michels installed 242 drilled shafts to support the piers for the new bridge. The installation of the drilled shafts was completed with the simultaneous use of up to four drill rigs. Utilizing barges, 233 drilled shafts were installed in the river. Michels crews also installed 7-foot and 10-foot permanent steel casing into bedrock for each shaft.

Read our white paper on this project. 

  • Michels scope of work is to install 242 drilled shafts to support the piers for anew bridge. The installation of the drilled shafts was completed with the simultaneous use of up to four drill rigs. Utilizing barges, 233 drilled shafts were installed in the river. Michels crews also installed 7-foot and 10-foot permanent steel casing into bedrock for each shaft.
  • Michels scope of work is to install 242 drilled shafts to support the piers for anew bridge. The installation of the drilled shafts was completed with the simultaneous use of up to four drill rigs. Utilizing barges, 233 drilled shafts were installed in the river. Michels crews also installed 7-foot and 10-foot permanent steel casing into bedrock for each shaft.

Projects

Michels built 458 secant piles and 100 caissons in 90 days for a 10-story, 600,000-square-foot building on the site of the new McDonald's corporate headquarters.

Deep Foundations

110 N Carpenter

Illinois

View Project

110 N Carpenter

Deep Foundations

Yesler Terrace

Washington

View Project

Yesler Terrace

Michels installed 857 H-piles 60 feet deep to bedrock for a deep foundation system for the R1VER project, a mixed-use waterfront development.

Deep Foundations

R1VER

Wisconsin

View Project

R1VER

Michels, one of North America's largest deep foundations contractors, built a secant pile structure for an underground power substation at the base of a multi-use building in the city's historic Third Ward.

Deep Foundations

Juneau Town Substation

Wisconsin

View Project

Juneau Town Substation

Michels performed the removal and replacement of walkway and pier structures along the eastern extent of the De Pere Dam.

Deep Foundations

De Pere Dam Walkway Replacement

Wisconsin

View Project

De Pere Dam Walkway Replacement

Michels was contracted to design and install secant shafts as temporary earth retention to allow for the excavation of approximately 71 feet below grade to install a new pump station.

Deep Foundations

Pump Station 4 Reconstruction

Illinois

View Project

Pump Station 4 Reconstruction

The only way to be truly satisfied is to do
what you believe is great work.

Steve Jobs

It's not bragging if you can do it.

Contact Us