Deep Foundations

Kaukauna Dam Tainter Gate Replacement

Kaukauna Dam Tainter Gate Replacement

Scope

Michels repaired and replaced 8 tainter gates and 9 existing concrete piers at the Kaukauna Dam. The dam was last rebuilt almost 90 years ago, and was severely deteriorating. Michels installed a cofferdam around the pier nosings along the upstream portion of the 9 concrete piers, performed select demolition, installed newly fabricated pier nosing, and formed and poured new concrete surface from river bed to the top of the concrete pier.

Crews removed the existing 8 tainter gates and demolished the tailwater portion of the existing piers. Nine new piers, 16 feet and 3-inches long by 5-feet wide by 15 feet tall, were formed and poured. Michels also procured tainter gates that were 20 feet wide by 14 feet tall.

  • Michels repaired and replaced 8 tainter gates and 9 existing concrete piers at the Kaukauna Dam. The dam was last rebuilt almost 90 years ago, and was severely deteriorating.

Projects

Michels built 458 secant piles and 100 caissons in 90 days for a 10-story, 600,000-square-foot building on the site of the new McDonald's corporate headquarters.

Deep Foundations

110 N Carpenter

Illinois

View Project

110 N Carpenter

Deep Foundations

Yesler Terrace

Washington

View Project

Yesler Terrace

Michels scope of work is to install 242 drilled shafts to support the piers for anew bridge. The installation of the drilled shafts was completed with the simultaneous use of up to four drill rigs. Utilizing barges, 233 drilled shafts were installed in the river. Michels crews also installed 7-foot and 10-foot permanent steel casing into bedrock for each shaft.

Deep Foundations

I-74 Mississippi River Bridge

Illinois

View Project

I-74 Mississippi River Bridge

Michels installed 857 H-piles 60 feet deep to bedrock for a deep foundation system for the R1VER project, a mixed-use waterfront development.

Deep Foundations

R1VER

Wisconsin

View Project

R1VER

Michels, one of North America's largest deep foundations contractors, built a secant pile structure for an underground power substation at the base of a multi-use building in the city's historic Third Ward.

Deep Foundations

Juneau Town Substation

Wisconsin

View Project

Juneau Town Substation

Michels performed the removal and replacement of walkway and pier structures along the eastern extent of the De Pere Dam.

Deep Foundations

De Pere Dam Walkway Replacement

Wisconsin

View Project

De Pere Dam Walkway Replacement

One learns more from listening than speaking...

Thor Heyerdahl

We listen to you.

Contact Us