Deep Foundations

Matalco

Matalco

Scope

Michels installed various forms of earth retention systems using steel sheet pile, secant shafts and drilled shafts. The customer required deep foundations in an area with a high water table. The earth retention systems Michels installed allowed crews to pour the foundations in a dry working area.

The project included the installations of 650 feet of 30-foot-long sheets, and 32 880mm diameter shafts 55-feet deep. Once the earth retention systems were in place, crews dewatered the area and installed one 42-inch shaft 70 feet deep.

  • Michels installed various forms of earth retention systems using steel sheet pile, secant shafts and drilled shafts. The customer required deep foundations in an area with a high water table. The earth retention systems Michels installed allowed crews to pour the foundations in a dry working area.

Projects

Michels built 458 secant piles and 100 caissons in 90 days for a 10-story, 600,000-square-foot building on the site of the new McDonald's corporate headquarters.

Deep Foundations

110 N Carpenter

Illinois

View Project

110 N Carpenter

Deep Foundations

Yesler Terrace

Washington

View Project

Yesler Terrace

Michels scope of work is to install 242 drilled shafts to support the piers for anew bridge. The installation of the drilled shafts was completed with the simultaneous use of up to four drill rigs. Utilizing barges, 233 drilled shafts were installed in the river. Michels crews also installed 7-foot and 10-foot permanent steel casing into bedrock for each shaft.

Deep Foundations

I-74 Mississippi River Bridge

Illinois

View Project

I-74 Mississippi River Bridge

Michels installed 857 H-piles 60 feet deep to bedrock for a deep foundation system for the R1VER project, a mixed-use waterfront development.

Deep Foundations

R1VER

Wisconsin

View Project

R1VER

Michels, one of North America's largest deep foundations contractors, built a secant pile structure for an underground power substation at the base of a multi-use building in the city's historic Third Ward.

Deep Foundations

Juneau Town Substation

Wisconsin

View Project

Juneau Town Substation

Michels performed the removal and replacement of walkway and pier structures along the eastern extent of the De Pere Dam.

Deep Foundations

De Pere Dam Walkway Replacement

Wisconsin

View Project

De Pere Dam Walkway Replacement

The only way to be truly satisfied is to do
what you believe is great work.

Steve Jobs

It's not bragging if you can do it.

Contact Us