Deep Foundations

Matalco

Matalco

Scope

Michels installed various forms of earth retention systems using steel sheet pile, secant shafts and drilled shafts. The customer required deep foundations in an area with a high water table. The earth retention systems Michels installed allowed crews to pour the foundations in a dry working area.

The project included the installations of 650 feet of 30-foot-long sheets, and 32 880mm diameter shafts 55-feet deep. Once the earth retention systems were in place, crews dewatered the area and installed one 42-inch shaft 70 feet deep.

  • Michels installed various forms of earth retention systems using steel sheet pile, secant shafts and drilled shafts. The customer required deep foundations in an area with a high water table. The earth retention systems Michels installed allowed crews to pour the foundations in a dry working area.

Projects

Michels built caissons and installed H-pipes for the Torrence Avenue Bridge along the Grand Calumet River.

Deep Foundations

IDOT Torrence Avenue

Illinois

View Project

IDOT Torrence Avenue

Michels installed 400 LF of sheet piling and 992 pipe piles to support construction in downtown Milwaukee.

Deep Foundations

Fiserv Forum

Wisconsin

View Project

Fiserv Forum

Michels built 458 secant piles and 100 caissons in 90 days for a 10-story, 600,000-square-foot building on the site of the new McDonald's corporate headquarters.

Deep Foundations

110 N Carpenter

Illinois

View Project

110 N Carpenter

Deep Foundations

Yesler Terrace

Washington

View Project

Yesler Terrace

Michels constructed secant compression ring launch and receiving shafts for a microtunneling project. The launch shaft was comprised of 46 intersecting 1-meter-diameter secant piles drilled to a depth of 54 feet. The receiving shaft was comprised of 38 intersecting 1-meter-diameter piles drilled to a depth of 52 feet.

Deep Foundations

Conduit 16 launch and receiving shafts

Colorado

View Project

Conduit 16 launch and receiving shafts

Michels scope of work is to install 242 drilled shafts to support the piers for anew bridge. The installation of the drilled shafts was completed with the simultaneous use of up to four drill rigs. Utilizing barges, 233 drilled shafts were installed in the river. Michels crews also installed 7-foot and 10-foot permanent steel casing into bedrock for each shaft.

Deep Foundations

I-74 Mississippi River Bridge

Illinois

View Project

I-74 Mississippi River Bridge

Quality means doing it right
when no one is looking.

Henry Ford

We do that.

Contact Us