Foundations

Pump Station 4 Reconstruction

Pump Station 4 Reconstruction

Scope

Michels, one of the largest deep foundations contractors in North America, was contracted to design and install secant shafts as temporary earth retention to allow for the excavation of approximately 71 feet below grade to install a new pump station. There are a total of 110, 1.5m diameter secant shafts in a 145-foot-diameter ring. Each shaft is installed to top of rock (71 feet) with an additional 10 feet into rock.

Upon completion of the secant shafts, a single shaft will be installed in the center of the ring to dewater the site. Once IHC Construction Companies LLC has excavated to final grade, Michels will come back and install 54 rock anchors to stabilize the building. Each rock anchor will be approximately 28 feet deep.

Michels used a Liebherr 36 drill rig to install Leffer segmental casing to the top of rock. A second Liebherr 36 with a modified kelly bar to allow for the flow of air was used with a cluster drill to hammer out the rock sockets.

Following the rock drilling, the pour crew tremie-poured each shaft to the top of the casing and then pulled casing out of the ground with a 1.5 meter Leffer oscillator. Every other shaft has an 82-foot-long W36x232 beam installed in its center.

By installing a watertight secant pile shaft, the pump station can be constructed which will help prevent flooding along the interstate.

  • Michels was contracted to design and install secant shafts as temporary earth retention to allow for the excavation of approximately 71 feet below grade to install a new pump station.
  • There are a total of 110, 1.5m diameter secant shafts in a 145-foot-diameter ring. Each shaft is installed to top of rock (71 feet) with an additional 10 feet into rock
  • By installing a watertight secant pile shaft, the pump station can be constructed which will help prevent flooding along the interstate.

Projects

Michels built caissons and installed H-pipes for the Torrence Avenue Bridge along the Grand Calumet River.

Deep Foundations

IDOT Torrence Avenue

Illinois

View Project

IDOT Torrence Avenue

Michels installed 400 LF of sheet piling and 992 pipe piles to support construction in downtown Milwaukee.

Deep Foundations

Fiserv Forum

Wisconsin

View Project

Fiserv Forum

Michels built 458 secant piles and 100 caissons in 90 days for a 10-story, 600,000-square-foot building on the site of the new McDonald's corporate headquarters.

Deep Foundations

110 N Carpenter

Illinois

View Project

110 N Carpenter

Michels installed 53 caissons in Massachusetts.

Deep Foundations

Cabot Tap Line Rebuild

Massachusetts

View Project

Cabot Tap Line Rebuild

Michels installed 36 transmission line caisson foundations that were between 6-7 feet in diameter and 30 feet deep in hard rock conditions.

Deep Foundations

W175 Transmission Line

Massachusetts

View Project

W175 Transmission Line

Deep Foundations

Yesler Terrace

Washington

View Project

Yesler Terrace

The only way to be truly satisfied is to do
what you believe is great work.

Steve Jobs

It's not bragging if you can do it.

Contact Us