Horizontal Directional Drilling

St. John's River Crossing Design Build

St. John's River Crossing Design Build

Scope

Michels completed a complex design-build construction project for the Jacksonville Electric Authority performing horizontal directional drilling (HDD), reaming and pullback operations for a 36” steel water main that spanned 6,575’. The alignment included two vertical curves and three horizontal curves in a congested area on a critical path timeline.


The project was constructed along the Arlington Expressway, a major east-west artery to downtown Jacksonville and the Jaguars football stadium. Months prior to construction the design-build team conducted daily meetings with key Florida Department of Transportation and local emergency management to develop a traffic and lane closure plan to consider peak traffic flows and allow safe and efficient construction. Once the project started, morning meetings initiated the next phase of traffic control each day. Much time was put into selecting the safest working environment for commuters and contractors alike.


Michels performed site preparation, pipe welding, coating, testing and HDD pullback assistance. The 36” steel pipe conformed to ASTM A-139 Longitudinally Seamed Grade C specs, and coating conformed to AWWA specifications that required 12-16 mils FBE 3M6233 ID and 12 mils FBE 3M6233 OD coating and 80 mils of Powercrete J ARO coating over exterior FBE.


Michels HDD operations began on the entry side with installation of about 160’ of 60” diameter steel containment casing and continued with installation of 200’ of 60” diameter steel casing on the exit side. The casings protected an existing 42” storm sewer that ran parallel to and eventually crossed above the proposed HDD alignment. A pilot hole intersect was performed under the river to reduce the downhole pressure of drilling.


Multiple strings of 36” water main were prestaged in three medians along the expressway between congested on/off ramps. A hard rock layer near the exit end of the crossing and several geometric design constraints presented unique challenges. The pull assembly was modified to achieve the successful combination of equipment, HDD tooling and pipe buoyancy control. The Herrenknecht 300T Thruster helped install the water main. It has a thrust and pulling force of up to 750 tonnes and is best for installing large diameter pipe in challenging geological conditions.


Michels crews worked 24 hours/day to complete six tie-in welds and the HDD pipe installation once the ramps were closed and had the ramps reopened within 10 days. The project was completed months ahead of the NFL season, which was the critical completion date.


  • Michels completed a complex design-build construction project for the Jacksonville Electric Authority performing horizontal directional drilling (HDD), reaming and pullback operations for a 36" steel water main that spanned 6,575'.
  • The project was constructed along the Arlington Expressway, a major east-west artery to downtown Jacksonville and the Jaguars football stadium.
  • Michels crews worked 24 hours/day to complete six tie-in welds and the HDD pipe installation once the ramps were closed and had the ramps reopened within 10 days.
  • Michels performed site preparation, pipe welding, coating, testing and HDD pullback assistance.
  • A pilot hole intersect was performed under the river to reduce the downhole pressure of drilling.

Projects

Horizontal Directional Drilling

Naval Facilities Engineering Command - Ford Island

Hawaii

View Project

Naval Facilities Engineering Command - Ford Island

<p>The Bakken Missouri River Crossing Project connects an existing compressor station located in the Bakken shale oil fields in Williams County, North Dakota, to a natural gas gathering system located in McKenzie County, North Dakota.</p>

Horizontal Directional Drilling

Bakken Missouri River Crossing

North Dakota

View Project

Bakken Missouri River Crossing

Horizontal Directional Drilling

Nexus Gas Transmission Pipeline

Michigan & Ohio

View Project

Nexus Gas Transmission Pipeline

Michels installed a 4,000-foot land-to-land and a 1,600-foot water-to-land installation of 16-inch pipe.

Horizontal Directional Drilling

Salem Lateral

Massachusetts

View Project

Salem Lateral

Michels trenchlessly installed 1,500 feet of 24-inch natural gas pipeline under a highway, creek and pond in a residential neighborhood.

Horizontal Directional Drilling

North Branch Pipe Replacement

Minnesota

View Project

North Branch Pipe Replacement

Michels completed a record setting horizontal directional drill (HDD) installation of an 18-inch diameter steel gas pipeline of 12,459 feet.

Horizontal Directional Drilling

Houston Ship Channel

Texas

View Project

Houston Ship Channel

One learns more from listening than speaking...

Thor Heyerdahl

We listen to you.

Contact Us